I received the specification shown below from a friend, an independent manufacturer's representative today. Yes this is the total expansion control spec. And a Construction Manager is soliciting budgets from subcontractors and materials suppliers for the project with this spec. This is a case where less (outline spec) is definitely not enough.
So What is Required There is no mention of the joint size, the type of movement, nor the total movement that must be accommodated. Must the joint accommodate seismic movement? This is a significant cost factor and severely limits the available joint designs. The loading for the floor joint is not specified. Will the joint see pedestrian, pallet jack, or fork truck traffic.
And Perhaps Superficial, but Still Important Are these joints with metal cover plates or an elastomer seal. If it is a seal, there may not be any exposed metal. Can the retainers holding the seal be extruded aluminum which is the industry standard? Are the joints surface applied, semi-recessed, or flush with the surrounding surfaces. Are the finish materials the same on both sides of the joint? Are corner joints required?
Keep Your Fingers Crossed I am sure my friend is wondering how to begin and if his budget numbers could possibly be relevant or remotely meaningful. I can see the list of budget qualifications being pages long just for expansion control. And the ultimate Construction Manager product budget? Stay tuned for multiple, dreaded Value Engineering exercises.
By the Way According to AIA standard agreements, the Budget is a document the Owner controls. The project must be designed and constructed to meet the Owner's budget. The Architect provides an Estimate of the Cost of the Work and the Contractor provides Estimates or Bids. It is best not to confuse budget with estimate.
SECTION 079502 - INTERIOR EXPANSION CONTROL
1.1 INTERIOR EXPANSION CONTROL SYSTEMS
A. Floor-to-Floor
1. Types: To be determined. 2. Exposed Metal: Stainless steel. 3. Fire-Resistance Rating: Same as adjacent construction.
B. Wall-to-Wall Joint Systems:
1. Types: To be determined. 2. Exposed Metal: Stainless steel. 3. Fire-Resistance Rating: Same as adjacent construction.
C. Ceiling-to-Ceiling Joint Systems:
1. Types: To be determined. 2. Exposed Metal: Stainless steel. 3. Fire-Resistance Rating: Same as adjacent construction.
CSI's specifying practice group discussed the concept of
outline specs and came to the conclusion that traditional outline specs will be
replaced. Most of the group members admitted they seldom produced or used
outline specs. When they do write outline specs, most are not using traditional
methods. Surprisingly, the overwhelming majority favored replacing outline
specs with preliminary project descriptions. So what do you think? Leave a
comment by signing in at the end of this posting.
So what do you think? Leave a comment by signing in at the
end of this posting. Then join the
group to receive notices of future meetings. It is FREE and it is not just for specifiers! Visit the CSI blog for more
information on this and previous practice group discussions.
Here is the presentation that prompted the discussion. The rationale for the poll results follows. Scroll
through the presentation using the arrow button below.
It is often difficult to produce outline specifications that
are consistent. All design team members do not use outlines based on the same
system and engineers prefer to use narratives rather than outlines to describe
the building systems. Tom Gilmore of Torti
Gallas and Partners, Inc. in Denver, CO, has solved this problem by
creating a single spreadsheet with all the standard text for all disciplines.
Each paragraph is a separate row. The text is selected for the particular
project by using Excel's Auto Filter function and then the text is modified as
needed.
Beware that your design contract may require outline specs
as a Design Development deliverable. AIA B101 - Owner Architect Agreement
ยง3.3.1 explicitly requires outline specs as one of the phase services. B101
does not define what constitutes an outline spec. So there may be some latitude
for architects within the bounds of accepted practice.
The group explored several examples of outline specs. CSI's
Project Resource Manual provides guidance on the format for producing the
outlines and shows an example illustrating some of the concepts. Masterspec and
SPECTEXT, two of the commercial spec systems available do not follow the same
format of the PRM example. This has caused confusion about what form an outline
spec should take.
Steve Lawrey of Vitetta
in Philadelphia, PA reported that outline specs are normally throw-away
documents. After they are produced, they are little used and the content must
be recreated when the construction specifications are written. Creating
information once and sharing the result should be the goal rather than
duplicating efforts.
Two alternatives to traditional outline specifications were
discussed: Multi-Purposed Specifications and Preliminary Project Descriptions
(PPD). Multi-purposed specifications rely on using a single document to produce
outline specifications and construction specifications. For outlines, most of
the document text is hidden, showing only text that is relevant to the current
design stage. As more information is developed, more of the specification text
is revealed, until the final construction spec is issued.
Preliminary project descriptions offer an entirely different
approach. Using UniFormat, the project description is arranged by system and
assembly instead of the MasterFormat divisions and sections used for
construction specifications. PPDs offer flexibility to describe multiple
options for the same assembly and the ability to document the reason for
selecting one of the options as the design solution. PPDs can be used
throughout the entire design process to capture the result of the process. Then
they can be used as a quality control checklist against the resulting
construction documents.
The consensus was clear. The group favored PPDs as the
preferred method to document projects during the early design stages. Clifford
Marvin of KPB Architects in
Anchorage, AK, a member of CSI's PPD Task Team pointed out that a PPD Guideline
is in progress and wholeheartedly recommended PPDs in place of outline specs. Download
the draft guideline
from the CSI website.